PERFORMANCE METHOD
RESISTANCE TO PRESSURE / LEAKING / NUMBER OF STARTING TIME
/ FLOW / LIFT JOINING /OIL-PROOF TEST OF PLASTIC MATERIALS / OIL PROOFNESS OF
CONNECTIONS / OPERATION /FATIGUE / LOW TEMPERATURE / BENDING
PRESSURE RESISTANCE TEST
*Pressure resistance
test shall be conducted on the discharge hose. Fitting a plug for blocking to
the end of discharge hose, a water pressure of 0.2kg/cm2 (gauge) shall be applied for 1minute and inspection, be made
on whether or not it can withstand it.
NUMBER OF STARTING TIME
*For test of number of starting times, kerosene shall be charge in
a 18liter can or drum can and the operating cylinder, be operated
after inserting the pump in other to check the number of operating
times before kerosene runs out automatically.
OIL PROOFNESS OF CONNECTIONS
*Cutting
the connection of pump, oil proofness test shall be conducted as follows.
(1)Pump connection shall be immersed in No.1 KEROSENE (oil temperature
20 5'c) stipulated in Japaness Industrial Standard JIS K 2203 (KEROSENES)
for 24 hours.
(2)Then, pump connection shall be taken out from the kerosene, joining
test stipulated in Item shall be conducted. But, it shall weight 3kg.
OIL PROOF TEST OF PLASTIC MATERIALS
*Test
shall be conducted as follows on the plastic materials of such parts as
discharge hose, suction pipe, operating cylinder, body, vane, vane
case, flange and such parts touching oil.
(1)The test sample shall be prepared in such a way that the
weight is approx. 5g.
(2)After
immersing the test sample in No.1 Gasoline stipulated in the Japaness Industrial Standards
JIS 2201 (Gasoline-s for Industrial Use), it shall be left as it is for
24 hours in the atmosphere and calculation, be made on the changing ratio
of weight from the following equation.
WEIGHT
AFTER - WEIGHT BEFORE X 100
RATIO (%)
TESTING(g)
TESTING(g)
WEIGHT CHANGING
= ----------------------------------------------------------------------------------------------------
WEIGHT
BEFORE TESTING
FATIGUE TEST
*For fatigue test,water shall be put in a 18liter can or drum can
shown in Table 5 and it shall be inserted in such a way that suction
pipe and discharge hose can enter it together. After operating the operating
cylinder 1000 times continuously at a speed of approx 45 times per minute.
LOW TEMPERATURE TEST
*For
fatigue test,water shall be put in a 18liter can or drum can shown in Table
5 and it shall be inserted in such a way that suction pipe and discharge
hose can enter it together. After operating the operating cylinder 1000
times continuously at a speed of approx 45 times per minute.